File #: 13-0725    Version: 1 Name:
Type: MOTION Status: PASSED
File created: 5/6/2013 In control: Public Works
On agenda: 6/4/2013 Final action: 6/4/2013
Title: CHANGE ORDER 3 - REPLACEMENT OF SE 15 AVENUE BRIDGES OVER MARCHETTA AND CARLOTTA RIVERS - Baker Concrete Construction, Inc. - add eight days to contract period at no additional cost
Sponsors: City Commission Regular Meeting
Attachments: 1. Commission Agenda Memo #13-0725, 2. Exhibit 1 - Change Order No 3
Title
CHANGE ORDER 3 - REPLACEMENT OF SE 15 AVENUE BRIDGES OVER MARCHETTA AND CARLOTTA RIVERS - Baker Concrete Construction, Inc. - add eight days to contract period at no additional cost