File #: 13-0271    Version: 1 Name:
Type: MOTION Status: PASSED
File created: 1/25/2013 In control: Public Works
On agenda: 6/4/2013 Final action: 6/4/2013
Title: CHANGE ORDER 3 (FINAL) - HORTT PARK COMMUNITY CENTER - Green Construction Technologies Inc. - $22,165.15 plus $2,216 in-house administration costs and 92 addtional work days to contract period.
Sponsors: City Commission Regular Meeting
Attachments: 1. Commission Agenda Memo 13-0271, 2. Exhibit 1 - Hortt Park Change Order 3 Final
Related files: 13-0688
 Title
CHANGE ORDER 3 (FINAL) - HORTT PARK COMMUNITY CENTER - Green Construction Technologies Inc. - $22,165.15 plus $2,216 in-house   administration costs and 92 addtional work days to contract period.