File #: 14-0912    Version: 1 Name:
Type: CONSENT MOTION Status: PASSED
File created: 7/15/2014 In control: Public Works
On agenda: 8/19/2014 Final action: 8/19/2014
Title: CHANGE ORDER 2 - ADDITIONAL WORK - SOUTHEAST 15 STREET BOAT LAUNCH AND MARINE COMPLEX IMPROVEMENTS - MBR Construction, Inc. - $29,618.88 - additional 8 calendar days to contract peirod
Sponsors: City Commission Regular Meeting
Attachments: 1. Commission Agenda Memo 14-0912, 2. Exhibit 1 - Change Order No. 2, 3. Exhibit 2 - Change Order No. 2 detailed basis scope for COPR #3, 4. Exhibit 3 - Change Order No. 2 detailed basis scope for COPR #5
Title
CHANGE ORDER 2 - ADDITIONAL WORK - SOUTHEAST 15 STREET BOAT LAUNCH AND MARINE COMPLEX IMPROVEMENTS - MBR Construction, Inc. - $29,618.88 - additional 8 calendar days to contract peirod